23 September 2024 26QB query -
Total Value of Consideration (Property Value) = 7643836
Payment type* = lumpsum
Amount paid/credited currently (B) * = 7643836
Total stamp duty value of the property (C) * = 5822200

above values are taken from index 2. I am getting warning because value difference is more than 20 %. What should I need to do for this?

23 September 2024 Have you registered the sale deed?
On what value stamp duty paid?

23 September 2024 Yes, registration is done.
stamp duty paid on 7643836 value.


23 September 2024 If C is taken from index II of current date, it should be accepted by the system, as it is less than B.
If system is not accepting it, then fill value as per B itself.

25 September 2024 Ok Thanks !
Then I will add same value as consideration value in stamp duty
Amount paid/credited currently (B) * = 7643836
Total stamp duty value of the property (C) * = 7643836

25 September 2024 Correct..
Good Luck.



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries