24 November 2008 May i please know about section 74 along with its exceptions of Indian Contract Act 1872

24 November 2008 When a contract has been broken, if a sum is named in the contract as the amount be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss or proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.

Explanation : A stipulation for increased interest from the date of default may be a stipulation by way of penalty.

Explanation : When any person enters into any bail bond, recognisance or other instrument of the same nature or, under the provisions of any law, or under the orders of the Central Government or of any State Government, gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to pay the whole sum mentioned therein.

25 November 2008


22 June 2023 "Sorry, I am not a featured member."
For featured members contact....
https://www.caclubindia.com/catalogue/featured.asp



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries