I need your help to find out guidelines, if any, issued by Customs about the documents required and process to be followed for finalisation of project import.
05 March 2021
The importer shall within three months from the - Customs clearance for home consumption of the last consignment of the goods or within such extended period as the proper officer may allow, submit a statement indicating the details of the goods imported together with necessary documents as proof regarding the value and quantity of the goods so imported in terms of this Regulation and any other document that may be required by the proper officer for finalisation of the contract. Documents such as import invoices and bill of entries required.
However we would like to know whether any process guidelines / list of documents required is issued by CBIC or any customs station (other than the process given in project import regulations)