17 March 2009 Standard hour for manufacturing two products M & N are 15hrs/unit & 20 hrs/unit respectively.Both products require identical kind of labour and standard wage rate per hour is Rs.5.In the year 2006, 10000 units or M & 15000 units of N were manufactured. The totals of labour hour actually worked were 450500 and actual wages bill cameto Rs.2300000.This include 12000 hours paid for @ rs.7/hrs and 9400 hours paid for rs.7.50/hrs, the balance had been paid at rs.5/hrs.Calculate labour rate variance,labour efficiency variance, labour cost variance

18 March 2009 LAbour rate variance 47500 adverse
LAbour efficiency variance 2500 adverse
Labour cost variance 50000 adverse

24 March 2009 thnka u sir
but please clear me that hw to solve the actual rates,how to put the actual rates on products m & n bcoz of three different rates.


30 June 2023 "Sorry, I am not a featured member."

For featured members contact....

https://www.caclubindia.com/catalogue/featured.asp



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries