06 December 2010 Please provide how DIN will be issued

06 December 2010 Step I. Obtain provisional DIN

The applicant is required to fill-up and submit form DIN-1 online for obtaining provisional DIN. Form DIN-1 is available under 'Apply for DIN' tab on the left hand side panel under DIN' link on the homepage of MCA portal.

Step II. Pay Din application fee

The applicant is required to login to the MCA portal and click on 'Pay Miscellaneous fee' link available under the 'Services' tab. Select 'DIN application fee' option and enter the provisional DIN. Applicant can make the payment of fee by using any of three modes of payment available on MCA portal. Form DIN-1 will be processed only after the DIN application fee is paid.

Step III. Dispatch of DIN application

The applicant is required to take a print-out of Form DIN-1 (containing provisional DIN generated online). Fill the service Request Number (SRN) of the fee paid. Sign the DIN application form manually and paste a good resolution photograph in the space earmarked. Attach the photocopies of the 'Proof of Identity' (Attach additional proof, if 'Father's name and 'Date of Birth' is not indicated in the 'Proof of Identity') and the 'Proof of Residence' with DIN application form and tick the relevant checkbox against the document name. Get the photograph and the attached supporting documents attested from an approved authority as specified in form DIN-1. The certifying authority must mention its particulars such as Name, COP No. etc, and affix its seal/ stamp.
Complete set of documents is required to be sent to MCA DIN Cell at Noida, by post, courier or hand delivery, as per convenience, within 60 days from the date of generation of provisional DIN online.

IV. Processing of DIN application

DIN application is received by MCA DIN Cell. DIN application form and attached supporting documents are scrutinized and if found in order, the provisional DIN is approved and activated in the system. If there is any defect in the DIN application, the provisional DIN is rejected. It takes about a week's time to complete this process. DIN approval/ rejection letter is generated and sent by post to the applicant. The status of application can also be tracked from the 'DIN Approval status' tab in the DIN corner.

V. Intimate approved DIN to your Companies

On approval of DIN, intimate your DIN to all the company(ies) (within a period of 30 days from the date of approval) in which you are a Director, in form DIN-2. Form DIN-2 can be downloaded and printed from the 'DIN' link on the homepage of MCA portal.

VI. Company to intimate your DIN to ROC

After the Director has intimated the DIN allotted to the company(ies), the Company(ies) is/are then required to intimate the DINs of its directors to the ROC in Form DIN-3 within a period of seven days of receiving form DIN-2.

VII. Post-approval changes in particulars of DIN-1

If there is any change in the particulars submitted in form DIN-1, File form DIN-4 for intimating the changes in the particulars within 30 days. For instance in the event of change of address of a director, he/ she is required to intimate this change by submitting Form DIN-4 along with the required attested documents with MCA DIN Cell.



source:http://www.mca.gov.in/Ministry/DIN_faq1.html



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries