12 February 2019 Pls advice, If I have make the DC for JOB work also I have generated E Way bill, so after compilation of Job work Eway bill required ??

12 February 2019 E way has to be generated for every movement of goods. So for sending the goods back after job work E waybill has to be generated.

12 February 2019 Thank you Dhruv Sir, but i have to generate eway bill again or that person who sending the the material after completion of job work


12 February 2019 Any one of the person can raise the e way bill.

12 February 2019 thank you Dhruv sir..!

12 February 2019 But, Sir, We are not purchasing the material, it's our materiel which we have sent them for some work, now they are sending the same, so we have to generate the Eway Bill ?? because they not agree for generate the eway bill

12 February 2019 While generating e way bill, select the option of job work in place of outward supply. Principal supplier also can generate e way bill.

12 February 2019 Thank You So Much Dhruv Sir...!




You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries