Booking of Exp more than Income


This query is : Resolved 

22 May 2009 Dear Friends,
Our company is Project Based Company.
We have taken a project.
We have given the whole contact to a sub contractor.
we have issued a Sale Bill of Rs. 6 Crore on our client.
The sub contractor has issued a bill of Rs. 7 Crore for the same project.
Can we book the whole Rs. 7 Crore Exp in the F Y 2008-09 or shoule we defer Rs. 1 Crore to next F Y?
The Project will be completed in the F Y 2010-11 & we are expecting overall profit from this.

22 May 2009 As per AS-7 construction contracts you have to recognise the profit based on percentage completion method, actual receipts and payments does not have any implications

22 May 2009 Yes i agree with the expert.

07 June 2011 Yes Manikanta is right


You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now



Similar Resolved Queries


loading


Unanswered Queries



CCI Pro



Answer Query



Company
31 October 2026
Accountants

sankaran and krishnan

New Delhi

B.Com

View Details
Company
Featured ARTICLESHIP 28 October 2026
CA- Inter and Articles

N N V Satish & Co.,

Hyderabad

CA Inter

View Details
Company
02 November 2026
Audit Executive

SRJP & Co LLP

Kochi

CA Inter

View Details
Company
30 October 2026
Asst Manager Accounts

Goodwin Pumps India Pvt Ltd

Chengalpattu

CA Inter

View Details
Company
ARTICLESHIP 25 October 2026
Article Intern (CA Articleship)

Arpan Bohra & Co

Hyderabad

CA Inter

View Details
Company
12 November 2026
Auditor

Oz Taxation

Vijayawada

Graduate (Any)

View Details
Company
13 November 2026
Chartered Accountant - Fresher

Neeraj Bhagat & Co

New Delhi

CA

View Details
Company
ARTICLESHIP 14 November 2026
Articleship Assistant

B Thejas and Associates

Bengaluru

CA Foundation

View Details