24 June 2013 a company has been formed i june 2012 ..
till 31st march 2013 compay has been incurred the project cost 1000000 and admin. cost is 2500000 ,so what is the treatment in financial statement??????

24 June 2013 What is the project nature & purpose?

24 June 2013 nature is the site development
and the purpose i.s promotional


24 June 2013 nature is the site development
and the purpose i.s promotional
and there is no revenue till date

24 June 2013 In case the project is nature of create any asset, you can keep the balance under Capital work in progress

Incase project expenses unable to construct assets and nature of revenue expenses then you debit to p&l a/c

25 June 2013 then we carry forward losses of current year to next year...
also section14A is attracted..in case
so then what is the treatment

25 June 2013 Reply which I have posted for accounting treatment, Income tax provision will be apply as per the act.



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries