Notification no108/1995

This query is : Resolved 

08 December 2011 I would like to know on non producing before the AC (forgot to do so) and cleared the goods meant for a project of UN recognised by G O I.

Profile Image

Guest

Profile Image

Guest (Expert)
10 December 2011 It will be deemed non-compliance and the remedies are :

1. Produce the Certificate from the United Nations Organization &

2. The Certificate from the Organization that the goods are approved by the Govt. of India.

12 December 2011 Not submitting the exemption certificate is just a technical lapse. You can submit later also. But the certificate date should be prior to dispatch.




You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries