i am in a touble i have passed my ipcc on may 2013 and done my itt and op before 31 oct but not yet submited my form i have done my franking today 2.1.2014 is thier any possible way so that my final attemt wont get delayed
In case Form No.103 is not submitted to the Institute’s Office within 30 days from the date of commencement of training, the procedure laid down by the Council for condonation of delay in submission of forms will apply.
Period of Delay
Condonation Fees to be paid
30 days beyond specified period
Rs. 100
31–180 days beyond specified period
Rs. 300
Beyond 181 days
Rs. 1000
1. If the delay is 31 days to 180 days beyond specified period, no documents are required to be submitted.
2. Following documents to be submitted if the delay is more than 181 days:
(a) Attendance record of the Articled Assistant.
(b) Original deed of Articles in Form 102, executed on non-judicial stamp paper.
(c) Certified copy of the work diary of the articled assistant.
(d) Stipend details with evidence in the form of Bank Pass Book/Statement.
Querist :
Anonymous
Querist :
Anonymous
(Querist)
02 January 2014
sir are you sure that delay upto 180 days wont need any document bcos it is mentioned in the form itself