23 May 2010
Sir, I have no weigh machine in my factory and I have to weigh material from outside (Loaded Vehcile). What intimation/procedure I should opt in this case. because after weight I can issue/raise excise bill. Kindly let me know what should I do in this case.
Please make a application to Division office through Range to obtain the Weighment Permission. Mention the nearest weighbrige, reason to sent. You are also required to prepare a challan in duplcate to sent the material to a weighbridge, Inward & outward time noting at main gate,stamp or slip of weight done. Check the weight as per Production and weigh as per Weigh-bridge, Seperate Register is required to maintain for the same. This permission is valid for one year as per request. For any mischief, duty will be recovered and goods may seazed.