02 June 2012 the purchase order is prepared but the bill is not available as on 31st March'12. whether provision has to be created for the aforementioned amount. such PO is towards purchase of Computer Equipment out of the fund sanctioned by AICTE towards MODROB Grant and the amount of PO is Rs. 788000/-.

02 June 2012 As per your query, it is found that purchase order is made. There may be type of cases: either advance is given and advance not given. we can treat the advance in the Capital work in progress with the detail of PO.The mention of the grant and sanction be made in the notes to accounts of final accounts

Avatar

Querist : Anonymous

Profile Image
Querist : Anonymous (Querist)
02 June 2012 how it can be classified as capital work in progress?
and as it is towards purchase of computer equipment can we pass the entry as Computer Software to be debited and the party against whom the PO was issued credited
one more thing that the advance was not given only the order was placed with the party-now what will be the accounting treatment in this scenario?


02 June 2012 I'd agree with the view of Phuljit, better to mention as notes.

However, consider these 2 possibilities:

If the eqpt. has been delivered by the vendor but the bill has not been submitted in Accounts deptt., then make the provision.

If no material is received as on the BS date, then better not pass any entry and follow the view as given by Phuljit.



You need to be the querist or approved CAclub expert to take part in this query .
Click here to login now

Join CCI Pro
CAclubindia's WhatsApp Groups Link


Similar Resolved Queries


loading


Unanswered Queries