File Content - 
		 Suggested Answer of Advanced Management 
Accounting 2016(May) 
 
 CA Ravi Shanker 
 [Topper of EIRC & NIRC] 
 
1. (a)  UK Ltd. prepared a draft budget for the next year as follows:    5 
Quantity 10,000 units 
 (₹.)=
Selling price per unit=60=
Variable cost per unit=
- Direct materials 
- Direct labour (2 hours x Rs. 6) 
- Variable overheads (2 hrs* Rs. 1) 
 
16 
12 
2 
contribution per unit 30 
Total budgeted contribution 3,00,000 
Total budgeted fixed contribution 2,80,000 
Total budgeted profit 20,000 
The board of directors are not satisfied with this draft budget and suggested the following 
changes for the better profit: 
(i) The budgeted profit  is ₹ 50.000, 
(ii) The company should spend ₹ 57,000 on advertisement and the target sales price up to ₹ 
64 per unit. 
(iii) It is expected that the sales volume will also rise, in spite of the price rise, to 12,000 units. 
In order to achieve the extra production capacity, however, the work force must be able to reduce 
the time taken to make each unit of the product. It is proposed to offer a pay and productivity 
deal in which the wages rate per hour is increased to ₹ 8. The hourly rate for variable overheads 
will be unaffected. 
You are required to calculate the target labour time require to achieve the target profit. 
 
Solution:  
Calculation of target labour time required to achieve target profit 
Particulars Amount (₹) 
Target Sales (12,000 units ×₹ -667557932;-667557934;) 7,68,000 
Less: Target/Budgeted Profit  50,000 
Total Target Cost 7,18,000 
Less: Fixed Cost 
- Existing                                                                                             ₹ 2,80,000 
- Advertisement                                                                                      ₹ 57,000 
 
 
3,37,000 
Total Target Variable Cost 3,81,000
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
÷-667558768;.-667558768;-667558777; -667558762;-667558769;-667558774;-667558763;-667558764; 12,000 
Target Variable cost per unit 31.75 
Less: Direct Material per unit 16.00 
Target Labour and variable overheads cost per unit 15.75 
÷-667558782;-667558781;-667558768;-667558762;-667558765; -667558782;-667558769;-667558779; -667558761;-667558782;-667558765;-667558774;-667558782;-667558781;-667558771;-667558778; -667558768;-667558761;-667558778;-667558765;-667558775;-667558778;-667558782;-667558779; -667558780;-667558768;-667558764;-667558763; -667558767;-667558778;-667558765; -667558775;-667558768;-667558762;-667558765; 
- Labour cost per hour                                                                                    ₹ 8 
- Variable Overhead per hour                                                                         ₹ 1 
 
 
9.00 
Target Labour hours per unit (A) 1.75 
Existing Lour hours per unit (B) 2 
Reduction in Labour hour required (A - B) 0.25 
 
 
(b) Supreme Prakashan Ltd. is in the business of publishing a leading newspaper which has a wide 
customer base. It measure quality of service in term of 
(i) Print quality 
(ii) On time delivery 
(iii) Number of damaged and unsold paper 
To improve its business prospects and performance, the company is considering installing a scheduling 
and tracking system which involve an annual additional cost of ₹ 3,00,000 beside equipments costing ₹ 
4,00,000 needed for the installation of system. 
To purchase the equipment, company is planning to utilize the proceeds of an investment fetching an 
annual income @ of 9%. 
Details regarding the present and future performance are given as under: -  
 Present Expected 
On-time delivery 85% 97% 
Variable cost per lot of newspaper damaged and unsold ₹=40=₹=40=
Fixed cost=50,000=50,000=
No. of lots of newspaper damaged and=unsold=6,00M=1,00M=
=
It is expected that each percentage increase in on time performance will result in revenue increase of ₹ 
36,000 per annum. Required contribution margin is 40%. 
 
Should Supreme Prakashan Ltd. install the new system?
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Solution:  
Determination of Incremental profit from installation of new system 
Particulars ₹ 
Increase in contribution {₹-667557935;-667557932;,-667557938;-667557938;-667557938;
-667557937;%×(-667557929;-667557931;%− -667557930;-667557933;%)} ×-667557934;-667557938;% 1,72,800 
Saving in variable coat of newspaper damaged (6000 - 1000) ×-667557934;-667557938; 2,00,000 
Total  3,72,800 
Less: Additional Operational Cost of new system 
- Additional                                                                                               ₹ 3,00,000 
- Opportunity Cost (4,00,000 ×₹ -667557929;%)                                                     ₹    36,000 
 
 
3,36,000 
Incremental Profit 36,800 
 
 
 
(c)A company is considering three alternative proposals for conveyance facilities for its sales personnel 
who have to do considerable travelling, approximately 20,000 kilometres every year. The proposals are 
as follows: 
(i) Purchase and maintain its own fleet of cars. The average cost of a car is ₹ 1,00,000. 
(ii) Allow  the Executive to use his own car and reimburse expenses at the rate of ₹ 1.60 per 
kilometer and also bear insurance costs. 
(iii) Hire cars from an agency at ₹ 20,000 per year per car. The company will have to bear 
costs of petrol, taxes and tyres. 
The following further details are available: 
Petrol ₹ 0.60 per km 
Repairs and maintenance ₹ 0.20 per km 
Tyres ₹ 0.12 per km 
Insurance ₹ 1,200 per car per annum  
Taxes ₹ 800 per car per annum 
Life of the car: 5 years with annual mileage of 20,000 kms 
Resale value: ₹ 20,000 at end of the fifth year 
Work out the relevant costs of three proposals and rank them.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Solution  
Determination of relevant cost of proposal of different options and its rank 
 (i) 
Own car 
(₹) 
(ii) 
Executive car 
(₹) 
(iii) 
Agency car 
(₹) 
Fixed Cost     
Depreciation on Car (₹ 1,00,000 – ₹ 20,000)/5 
Insurance Cost 
Taxes 
16,000 
1,200 
800 
- 
1,200 
- 
- 
- 
800 
Total (A) 18,000 1,200 800 
Fixed cost per km (A ÷-667557936;-667557938;,-667557938;-667557938;-667557938; -667558772;-667558770;-667558764;) 0.90 0.06 0.04 
Running and Maintenance Cost  
- Petrol 
- Repair and Maintenance 
- Tyre 
 
0.60 
0.20 
0.12 
 
- 
- 
- 
 
0.60 
- 
0.12 
Reimbursement  - 1.60 1.00 
Total cost per km. (B) 1.82 1.66 1.76 
Cost for 20,000 (B ×-667557936;-667557938;,-667557938;-667557938;-667557938;) 36,400 33,200 35,200 
Ranking of alternative proposals III I II 
Decision: Second alternative i.e. use of own car, is the best alternative from company‟s point of view.  
 
(d) The cost per unit of transporting goods from the factories X, Y, and Z to destination A, B, C, and D 
and the quantities demanded and supplied are given:       5 
Factories Destinations Supply 
A B C D 
X 25 50 20 25 100 
Y 30 40 35 10 250 
Z 20 10 25 35 200 
Demand 250 100 150 50 550 
Answer the following question with reasons taking u3 as zero while calculating ui & vj : 
(i) Is this solution is optimum? 
(ii) If yes, can there be any alternate optimum solution?
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Solution:  
Since, question is silent about method to be used in determination of initial solution we use Vogel‟s 
Approximation Method (VAM):  
Initial solution by using VAM: 
Factories Destination Supply  
X × 
25 
× 
50         20 
100 × 
25 
100/- 
Y 
30 
150 × 
40 
 
35 
50 
10 
50 250/200 
Z 
20 
100 
10 
100 × 
25 
˟=
35=
20M/100=
Demand 250/150/0 100/0 150/50/0 50/0  
 
Penalty  
5 30↑=R=25=
R=-=R=15=
R=-=5↑=M=
10↑=-=10=-=
=
Since, numbers of allocated cells are equal to m+n-1/ R+C-1 (i.e. Number of Rows + Number of=
Column -=1) hence above solution is ready for the optimality test. =
=
Determination of value of ui and vj by using cij = ui  + vj, where u3 is assumed 0 as specified in the 
question.  
Factories Destination ui 
X  
25 
 
50 
        20 100  
25 
u1 = -5 
Y 30 150  
40 
 
35 
50 10 50 u2 = 10 
Z 20 100 10 100  
25 
 
35 
u3 = 0 (assume) 
vj v1 = 20 v2 = 10 v3 = 25 v4 = 0   
 
Penalty 
 
5 
 
5 
 
5 
 
- 
 
20 
←=
20=
=
R=
=
R=
=
10=
=
R=
=
R=
=
R=
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Determination of opportunity cost or cell evaluation of each unallocated/empty cell (i, j) by using ∆ij = 
cij – (ui + vj): 
Factories Destination ui 
X  
 
25 
 
 
50 
         
 
20 
100  
 
25 
u1 = -5 
Y  
 
30 
150  
 
40 
 
 
35 
50  
 
15 
50 u2 = 10 
Z  
 
20 
100  
 
10 
100  
 
25 
 
 
35 
u3 = 0 
(assume) 
vj v1 = 20 v2 = 10 v3 = 25 v4 = 0   
 
Since, value of ∆ij are non negative (either zero or more than zero) hence above solution is optimum. If 
∆ij is zero then it represents alternative solution. Number of alternative solution is totally depended upon 
number of ∆ij came as zero. In the above solution one alternative solution can be obtained by 
reallocating units by using loop.  
 
2. (a)  A  company  produces  and  sells  a  single  product.  The  cost  date  per  units for  the  years  2017  is 
predicted as below:          8 
 ₹=Per unit=
Direct material =35=
Direct labour =25=
variable overheads=15=
Selling price=90=
The company has forecast that demand for the product during the year 2017 will be 28,000 units. 
However to satisfy this level of demand,==
Production quantity will be increased?=
There are no opening stock and closing of the product.=
The stock level of material remains unchanged throughout the period.=
The following additional information regarding cost and revenue are given:=
- 12.5% of the items delivered to customers will be rejected due to specification failure and will 
require free replacement. The cost of delivering the replacement item is ₹ 5 per unit. 
- 20% of the items produced will be discovered faulty at the inspection stage before they are 
delivered to customers. 
- 10% of the direct material will be scrapped due to damage while in storage. 
Due to above, total quality costs for the year is expected to be ₹ 10,75,556. 
45 10 30 
20 
0 35
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
The company is now considering the following proposal: 
a. To introduce training programmes for the workers the workers which, the management of the 
company believes, will reduce the level of faulty production to 10%. This training programme 
will cost ₹ 4,50,000 per annum. 
b. To avail the services of quality control consultant at an annual charges of ₹ 50,000 which would 
reduce the percentage of faulty items delivered to customers to 9.5%. 
You are required to: 
(i) Prepare a statement of expected quality cost the company would incur if it accepts the 
proposal. Costs are to be calculated using the four recognized quality costs heads.  
(ii) Would you recommend the proposal? Give financial and non-financial reasons. 
 
Solution 
(i) Determination of rejected items, faulty items and scrap items before and after 
acceptance of proposal 
Particulars Before acceptance 
(units) 
After acceptance 
(units) 
Demand 28,000 28,000 
Add: Rejected items by customers 4,000 
( 28000 × 12.5
87.5) 
2,940 
( 28000 × 9.5
90.5) 
Units delivered to customers 32,000 30,940 
Faulty units 8,000 
(32,000 × 20
80) 
3,438 
(30,940 × 10
90) 
Gross Production  40,000 34,378 
Add: Scrapped due to damage in storage 4,444.44 
(40,000 × 10
90) 
3,820 
(34,378 × 10
90) 
 
Statement of expected quality cost for the 2017 of Company before and after acceptance of 
proposal 
Particulars Before acceptance (₹) After Acceptance (₹) 
Preventive Cost 
- Training programme cost 
 
- 
 
4,50,000 
Appraisal Cost 
- Annual Quality control consultant charges 
 
- 
 
50,000 
Internal Failure Cost 
- Scrap item  
 
1,55,556 
 
1,33,700
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
 
- Faulty units 
(4,444.44 ×35) 
6,00,000 
(8,000 ×35) 
(3,820 ×35) 
2,57,850 
(3,438 ×75) 
External Failure cost 
- Rejected item cost 
 Manufacturing cost 
 
 Delivery cost 
 
 
3,00,000 
(4,000 ×75) 
20,000 
(4,000 ×5) 
 
 
2,20,500 
(2,940 ×75) 
14,700 
(2,940 ×5) 
Total cost of quality 10,75,556 11,26,750 
 
(ii) On the pure financial reason based TQM and proposal should not be accepted because it 
increases cost by 51,194. 
But based on non-financial reasons it should be accepted because it reduce external failure 
(rejected items) by 3% and faulty units production by 10% which will image of company in 
the eyes of customer. 
Note: Scrap items valued at material acquisition cost, Faulty units are valued at manufacturing cost 
whereas rejected items are valued at total variable cost (Manufacturing cost + Delivery cost). 
 
(b) A company manufactures a product Y in addition to other products by using the same machines in 
department A and department B. 
The usage details are: 
Per unit of Product Y  Department A Department B 
Usage Rate Usage Rate 
Direct Material 8 kg ₹=Q=4 kg=₹=S=
Direct Labour=2 hours=₹=14=3 hours=₹=12=
Basis of overhead recovery are given below:=
=Department A per ₹ of 
direct material 
₹ 
Department B per direct 
labour hour 
₹ 
Variable overheads 0.80 2.00 
Fixed overheads 2.20 3.00 
Other Details are: 
salue of Plant & Machinery in department A is ₹ 22 Lacs and in department B is ₹ 18 Lacs. 
The Working Capital requirement of Product Y based on a target volume of output of 2,000 units per 
month is estimated at ₹ 2,72,800 per annum which is 40% of the potential capacity.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Required: -  
(i) Calculate the selling price of Product Y to ensure contribution equivalent to 25% of investment 
made. 
(ii) If Product Y is a new product about to be launched in the market, on what basis should the price be 
fixed and what would be the minimum price? 
(iii)If Product Y is a well established product, what should be the basis for price  fixing and what would 
be the minimum price? 
 
Solution:  
Computation of total cost of Product Y 
Particulars ₹ 
Direct Material  
- Deptt. A      (8 kg ×₹ -667557934; ) 
- Deptt. B      (4 kg ×₹-667557932; ) 
 
32 
24 
 
 
56.00 
Direct Labour 
- Deptt. A      (2 hour ×₹ -667557937;-667557934; ) 
- Deptt. B      (3 hour ×₹ -667557937;-667557936; ) 
 
28 
36 
 
 
64.00 
Variable overheads 
- Deptt. A      (₹ 32 ×₹ -667557938;.-667557930;-667557938; ) 
- Deptt. B      (3 hour ×₹ -667557936;.-667557938;-667557938; ) 
 
25.60 
6.00 
 
 
31.60 
Total Variable cost per unit 141.60 
Fixed overheads 
- Deptt. A      (₹ 32 ×₹ -667557936;.-667557936;-667557938; ) 
- Deptt. B      (3 hour ×₹ -667557935;.-667557938;-667557938; ) 
 
70.40 
9.00 
 
 
79.40 
Total Cost   261 
 
Determination of total investment 
Particulars Amount 
(₹) 
Portion of Plant and Machinery 
- Deptt. A     (₹ 22,00,000 ×-667557934;-667557938;%) 
- Deptt. B     (₹ 18,00,000 ×-667557934;-667557938;%) 
 
8,80,000 
7,20,000 
Working capital  2,72,800 
Total 18,72,800
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
(i) Calculation of selling price of product Y 
Particulars (₹) 
Variable cost per unit 141.60 
Add: Contribution per unit 
(18,72,800 ×-667557936;-667557933;% ×-667557937;/-667557937;-667557936;)/2000 
19.51 
Selling price per unit 161.11 
 
(ii) If product Y is new product and about to be launched in the market then company should 
implement penetration strategy i.e. selling price should be variable cost per unit  
(iii) If Product Y is a well established product in the market then minimum selling price should be 
total cost per unit i.e. ₹ 261. 
 
 
3. (a)  Division  X  and  Y  are  two  division  of  XY  Ltd.,  which  operates  as  profit  centres.  Division  X 
makes and sells product  X. The budgeted income statement of Division  X, based on a sales volume 
of 30,000 units, is given below: 
Budgeted Income Statement of Division X 
Particulars ₹=in „000=
Sales Revenue=6,00M=
Component purchase costs=1,05M=
Other variable costs=1,68M=
Fixed costs=48M=
Variable marketing costs=27M=
Fixed marketing overheads=85R=
Operating profit=1,66R=
=
The  manager  of= Division= X  suggests= that= sales  can  be= increased  by= 9,600  units,= if= the  selling  price  is=
reduced by ₹ 20 per unit from the present price of ₹ 200 per unit and that for this additional volume, no 
additional fixed costs will be incurred. 
 
Division Y makes a company Y which is sold outside at a price of ₹ 50 per unit. 
 
Division  X  presently  uses  a  component  which  is  purchased  from  outside  at  ₹  35  per  unit.  This 
component  is  similar  to  component  made  by  Division  Y.  Division  Y  can  make  this  component  for 
Division  X  with  a  minor  modification  in  specification  which  would  cause  reduction  in  direct  material 
cost for the Division Y by ₹ 1.5 per unit and would require extra labour hour of 1 per unit at the rate of ₹ 
1.5 per hour.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Further the Division Y will not incur variable selling marketing cost on units transferred to the Division 
X‟s manager has offered to buy the component from Division Y at ₹ 25.00 per unit. Division Y has the 
capacity to produce 85,000 units. 
The current budgeted information of Division Y are as follows: 
Number of units sold outside 60,000 units @ ₹ 50 per unit, variable cost including material and labour ₹ 
15  per  unit,  variable  marketing  cost  ₹  3  per  unit,  operating  profit  ₹  12,00,000  and  fixed  overheads  ₹ 
7,20,000. 
Advise 
(i) Should  the  division  X  reduce  the  selling  price  by  ₹  20  per  unit  even  if  it  is  not  able  to  procure  the 
component from Division Y at ₹ 25 per unit?    
(ii) Should the Division Y be willing to supply 39,600 units to Division X at ₹ 25 per unit? 
Support each of your conclusions with appropriate calculations. 
 
Solution: 
(i)  
Division X 
Statement of profit if selling price reduced by ₹ 20 and units are not procured from Division Y 
Particulars (₹) 
Sales Revenue (39,600 ×₹ -667557937;-667557930;-667557938;) 71,28,000 
Less: Variable cost  
- Component cost (39,600 ×₹ -667557935;-667557933;) 
- Other variable costs (39,600 ×₹ -667557933;-667557932;) 
- Marketing cost (39,600 ×₹ -667557929;) 
 
13,86,000 
22,17,600 
3,56,400 
Contribution  31,68,000 
Less: Fixed Cost  
- Manufacturing cost 
- Marking cost 
 
4,80,000 
8,55,000 
Revised Operating profit (A) 18,33,000 
Existing operating profit (B) 16,65,000 
Incremental operating profit (A - B) 1,68,000 
 
Division X should reduce its selling price by ₹ 20 even if it is not able to procure the component from 
Division Y at ₹ 25 per unit.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
(ii)  
Division Y 
Statement of revised profit if 39,600 units transferred to Division X at ₹ 25  
Particulars (₹) 
Sales Revenue  
- Division X (39,600 ×₹ -667557936;-667557933;) 
- Market (45,400 ×₹ -667557933;-667557938;) 
 
9,90,000 
22,70,000 
Total Revenue  32,60,000 
Less: Variable cost  
- Material and labour cost (85,000 ×₹ -667557937;-667557933;) 
- Marketing cost (45,400 ×₹ -667557935;) 
 
12,75,000 
1,36,200 
Contribution  18,48,800 
Less: Fixed Cost  7,20,000 
Revised Operating profit (A) 11,28,800 
Existing operating profit (B) 12,00,000 
Incremental operating profit (A - B) (71,200) 
 Division Y should not transfer units to Division X at ₹ 25.  
 
(b)   A company is engaged in manufacturing two products M and N. Product M uses one unit of component 
P and two units of component Q. Product N uses two units of components p, one unit of component Q 
and two units of component R. Component R which is assembled in the factory uses one unit of 
component Q. Components P and Q are purchased from the market. The company has prepared the 
following forecast of sales and inventory for next year: 
 Product M Product N 
Sales (in units) 80,000 1,50,000 
At the end of the year 10,000 20,000 
At the beginning of the year 30,000 50,000 
  The production of both the products and the assembling of the component R will be out uniformly 
throughout the year. The company at present orders its inventory of P and Q in quantities equivalent to 3 
months production. The company has compiled the following data related to two components: 
 P Q 
Price per unit (₹)=20=8=
Order placing cost per order (₹)=1,50M=N,500=
Carrying cost per annum=20B=20B=
Required: 
(i) Prepare a Budget of production and requirements of components for next year. 
(ii) Suggest the optimal order quantity of components P and Q.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Solution: 
(i)  
Statement of Production Budget for Product M & N 
Particulars M N 
Inventory at the end of year 10,000 20,000 
Add: Sales 80,000 1,50,000 
Total Requirements  90,000 1,70,000 
Less: Inventory at the beginning of the year 30,000 50,000 
Required Production  60,000 1,20,000 
 
Budgeted Requirements of Components P, Q and R 
Particulars P Q R 
For product M: 
- P (60,000 ×-667557937;) 
- Q (60,000 ×-667557936;) 
 
60,000 
- 
 
- 
1,20,000 
 
- 
- 
For Product N: 
- P (1,20,000 ×-667557936;) 
- Q (1,20,000 ×-667557937;) 
- R  (1,20,000 ×-667557936;) 
 
2,40,000 
- 
- 
 
- 
1,20,000 
- 
 
- 
- 
2,40,000 
For Component R: 
- Q (3,60,000 ×-667557937;) 
 
- 
 
2,40,000 
 
- 
Total  3,00,000 4,80,000 2,40,000 
 
(ii) Optimum Order Quantity/ Economic Order Quantity =  2
  
Where,  
A = Annual Consumption (in case of M = 3,00,000 and N = 4,80,000) 
O = Ordering Cost per order (i.e. ₹ 1,500 per order) 
C = Carrying Cost per unit per annum (Purchasing cost per unit ×-667558817;-667558817;-667558821; -667558820;-667558816;-667558815; %) 
 
Component M =  2 ×3,00,000 ×1,500
20 ×20% = 15,000 
 
 
Component N =  2 ×4,80,000 ×1,500
8 ×20% = 30,000
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
4 (a)  A company operates a standard cost system to control the variable works cost of its only product. 
The following are the details of actual production, costs and variances for November, 2015.  
Production and cost (actual) 
Production 10,000 units 
Direct Materials (1,05,000 kg.) ₹=5,20,000=
Direct Labour (19,500 hrs.F=₹=3,08,000=
Variable Overheads=₹=4,10,000=
 
Cost variances 
Direct materials –=Price =₹=5,000 (FF=
Direct materials=–=Usages==₹=25,000 (A)=
Direct labour –=Rate==₹=15,500 (A)=
Direct labour –=Efficiency==₹=7,500 (FF=
Variable overheads=₹=10,000 (A)=
The Cost Accountant finds that the original standard cost data for the product is missing from the cost=
department files. The variance analysis for December, 2015 is held up for want of this data.=
You are required to calculate :=
(iF Standard price per kg of direct material.   
(ii) Standard quantity for each unit of output. 
(iii)Standard rate of direct labour hour. 
(iv) Standard time for actual production. 
(v) Standard variable  overhead rate. 
Solution: 
i) Material Price Variance = (Actual Quantity × Standard Price) – (Actual Quantity × Actual 
price) 
500(F) = (1,05,000 × Standard Price) – (5,20,000) 
Standard Price = ₹ 5,25,000
1,05,000  
Standard Price = ₹ 4 per kg 
 
ii) Material Usages Variance = (Standard Quantity × Standard Price) – (Actual Quantity × 
Standard price) 
25,000(A) = (Standard Quantity × ₹ 5) - (1,05,000 × ₹ 5) 
Standard Quantity × ₹ 5 = ₹ 5,25,000 -₹ 25,000 
Standard Quantity = ₹ 5,00,000
₹ 5 
Standard Quantity = 1,00,000 kg
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
iii) Labour Rate Variance = (Actual Hours × Standard Hours) – (Actual Hours × Actual Rate) 
15,500(A) = (19,500 × Standard Rate) - ₹ 3,08,000 
Standard Rate =  ₹ 2,92,500
19,500  
Standard Rate = ₹ 15 
 
iv) Labour Efficiency Variance = (Standard Hours × Standard Rate) – (Actual Hours × Standard 
Hours) 
7500(F) = (Standard Hours × ₹ 15) – (19,500 × ₹ 15) 
Standard Hours = ₹ 3,00,000
₹ 15 
Standard Hours = 20,000 hours 
 
v) Variable overhead Variance = Standard Overheads – Actual Overheads 
10,000(A) = Standard Overheads - ₹ 4,10,000 
Standard Overheads = ₹ 4,00,000 
Standard Variable Overheads = Standard Hours × Standard Rate 
₹ 4,00,000 = 20,000 × Standard Rate 
Standard Rate = ₹ 4,00,000
20,000 = ₹ 20 
 
(b) After 15 days of working the following progress is noted for the network of an erection job: 
(i) Activity 1-2, 1-3, and 1-4 competed as per original schedule. 
(ii) Activity 2-4 is in progress and will be complete in 3 more days. 
(iii)Activity 3-6 is in progress and will need 18 days more for completion. 
(iv)  Activity 6-7 appears to present some problem and its new estimated time of completion is 12 days. 
(v) Activity 6-8 can be completed in 5 days instead of originally planned for 7 days. 
You are required to: 
(i) Update the above diagram after 15 days of the start of work based on the assumption given above. 
(ii) Write down the critical path with total project duration. 
 
Solution:  
i) Statement of Revised Duration of Activities 
Activity Calculation Revised Duration 
1-2 - 9 
1-3 - 10 
1.4 - 6 
2-4 (15 + 3 –=9)=V=
2-5 - 18
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
3-4 - 5 
3-6 ( 15 + 18 - 10) 23 
4-7 - 20 
5-7 - 8 
6-7 - 12 
6-8 - 5 
7-8 - 6 
 
 
 
 
        9  
     9           8 
 
 6 20 6 
 
 10  
                                            12 
       23   5 
 
 
ii) Possible Paths and its duration:  
Possible Paths Calculation Duration (Days) 
1-2-5-7-8 9+18+8+6 41 
1-2-4-7-8 9+9+20+6 44 
1-4-7-8 6+20+6 32 
1-3-4-7-8 10+5+20+6 41 
1-3-6-7-8 10+23+12+6 51 
1-3-6-8 10+23+5 38 
 
Critical Path is 1-3-6-7-8 and its duration is 51 days. 
 
 
 
2 
8 7 4 1 
3 6 
5
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
5. (a) MP Ltd. has developed a special product. Details are as follows: 
The product will have a life cycle of 5,000 units. It is estimated that market can absorb first 
4,500 units at ₹ 64 per unit and then the product will enter the “decline” stage of its life 
cycle. 
The company estimates the following cost structure: 
Direct Labour ₹=6 per hour=
Other variable costs==₹=19 per unit=
=Fixed costs will be ₹ 40,000 over the life cycle of the product. The labour rate and both of 
these cost will not change throughout the product‟s life cycle. 
The first batch 0f 100 units will take 1,000 labour hours to produce. There will be 80% 
learning curve that will continue until 2,500 units have been produced. Batches after this 
level will each take the same amount of time as the 25th batch. The batch size will always be 
100 units. 
Calculate: -  
(i) The cumulative average time per batch for the first 25 batches. 
(ii) The time taken for the 25th batch if average time for 24 batches is 359.40 hours. 
(iii)The average selling price of the final 500 units that will allow the company to earn a total 
profit of ₹ 80,000 from the product. 
(Note: Learning coefficient is -0.322 for learning rate of 80%) 
The values of Logs have been given for calculation purpose: 
log2 = 0.30103, log3 = 0.47712, log5 = 0.69897 
antilog of 2.534678 = 342.51 
antilog of 2.549863 = 354.70 
antilog of 2.555572 = 359.40 
antilog of 2.567698 = 369.57 
Solution: 
(i) Determination of average time required per batch for the first 25 batches. 
Average accumulated hours (y) = axb 
When, 
a = Time required for first batch 
x = cumulated batch 
b = learning co- efficient
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
   3.000- 0.1573 
   2.8426 
 
Y = axb 
log y = log 1000 + (-0.322) × log 25 
log y = 3.0000 + (-0.322) × 2 × log 5 
     = 3.0000 + (-0.322 × 2 × 0.69897) 
     = 3.0000 – 0.44501 
    = 2.5498 
Antilog of 2.5498 = 354.70 
(ii) Time required for 25th batch 
= (Total accumulated hour upto25th batch ) – (cumulated hour upto 24th batch) 
= (354.70 × 25) – (359.40 × 24) 
= 8867.50 – 8625.60 
= 241.90  
(iii) Computation of aver5age selling price of final 500 units to earn total profit of 80,000 
Particulars (₹) 
Labour cost 
- First 2500 units (8867.50 × ₹6) 
- Last 2500 units (241.90 × 25 × ₹ 6)  
 
53205 
36285 
Add: other variable cost (5000 × ₹ 19)   
 
95000 
1,84,490 
Add: Fixed cost                   40.000 
Total  2,24,490 
Add: Desired Profit 80,000 
3,04,490 
(-) Sales Revenue of first 45,000 units (4,500 × ₹ 64) 2,88,000 
Sale Revenue from 500 units  16,490 
÷ No of units 500 
32.98 
  
5. (b)  XY Ltd. is manufacturing a consumer product and doing marketing through 200 depots all 
over the   country. The company is considering closing down the depots and resorting to 
dealership arrangements. The total turnover of the company is ₹ 160 crores per annum. The 
following information is given for each depot. 
 ₹ in lakhs 
Annual turnover  80.00 
Average inventory 16.00 
Administrative expenses per annum 1.60 
Staff salary per annum 2.88
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
The inventory carrying cost is 16% p.a. which is also the interest rate prevailing in the market 
for working capital finance. The other fixed cost per annum is ₹ 16 crores. Marketing through 
dealers would involve engaging dealers for each area. The dealers will assure minimum sales 
for each area. This would result in increasing the capacity utilization from 80% to 100%. At 
present the company‟s P/V ratio is 20%. Marketing through dealers would involve payment of 
commission of 8% on sales. Half of the existing depot staff will have to be absorbed in the 
company. The dealer will deposit ₹ 3.20 crores with company on which interest at 12% p.a. will 
be paid. 
You are required to work out the impact on profitability of the company by accepting the 
proposal. 
 
Solution: 
Statement of incremental profitability on acceptance of proposal 
Particulars  (₹ lakh) 
Incremental Revenue  
Incremental contribution (4000 × 20%) 800 
Saving of staff salary (2.88 × 50% × 200) 288 
Administration expense (1.60 × 200)  320 
Interest Saving on Investor deposits (16 × 200 × 16%)   512 
Deposit from dealers (3.20 × 200 × 16%)  102.40 
 2022.40 
Less:  
- Commission (20,000 × 8%) 
- Interest payments (3.20 × 200 × 12%) 
 
1600 
76.80 
Incremental Profit 345.60 
 
Working Note: 
(1) Total turnover at 80%    = 160 crores 
Additional turnover   160 -667558817;-667558820;-667558817;-667558816;×20
80    = 40  
Total               = 200 crores 
(2) It is assumed other fixed cost will not affected with decision. 
(3) Administration expenses are treated as specific cost. 
(4) Since administration expanses, staff salary & deposit are taken as per depot basis.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
 
6.   (a) A manufacturing unit of ABC co. Ltd. has presented the following details: - 
Average units produced and sold per month 2,40,000 
No. of workers 80 
Sales value ₹=60 Lacs=
Contribution=₹=24 Lacs=
Wage rate =₹=5 per unit=
The production manager purposes to introduce a new automated machine due to which 
following changes will take place:=
1) No. of units produced and sold are expected to increase by 20%. 
2) No. of workers will be reduce to 60. 
3) With a view to provide incentive for increased production, production manager intends to 
offer 1% increase in wage rate for every 3% increase in average individual output achieved. 
4) Decrease in selling price by 2%. 
Required:  
Calculate amount of extra contribution after introduction of new automated machine and give 
your recommendations. 
Solution:  
Statement of additional contribution 
 Before After Increment 
No. of units (A)  2,40,000 (₹) 2,88,000 (₹) 48,000 (₹) 
Sales Required 25.00 24.50 - 
(-) Variable cost p.u.    
- Wages 5 6  
- Others 10 10  
Contribution (B) per unit 10 8.50  
Total Contribution(A × B) 24,00,000 24,48,000 48,000 
 
Extra contribution after introduction of new automated machine is ₹ 48,000. 
Working Note 
Increase in average individual output:-  
Total Budgeted production (2,40,000 × 120%)  2,88,000 units 
÷ No. of worker      60 
Revised Production    4800 
(-) Existing Production    3000 
Increase in Production    1800 
% increase in Production   = 1800 ×100
3000  = 60%
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Revised Rate   = ₹ 5 + ₹ 5 × 60% ×1
3% 
      = ₹ 5 + ₹ 1 
      = ₹ 6 
 
6. (b) A manufacturer produces two types of products i.e. X and Y. Each of these products requires     
three types of processing. The processing time for processing each unit and the profit per unit are 
given in the following table: 
 Product 
X 
(hr/unit) 
Product 
Y 
(hr/unit) 
Available capacity per day 
(hr.) 
Process I 12 12 840 
Process II 3 6 300 
Process III 8 4 480 
profit per unit (₹)=R=T==
  =Applying Graphical method, how many units of each product should the company produce=
per   day in order to maximize profit?=
=
Solution: 
  Let 
  x = No. of units Production of Product x 
 y = Number of units Produced of Product y 
Objective 
Maximisation of Profit 
Maximize (z) = 5x + 7y 
Subject to Constraints 
  12x + 12y ≤ 840 
  3x +6y      ≤ 300 
  8x + 4y     ≤ 480 
   x ≥0; , y ≥ 0
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
Equation – (i) 
     12x + 12y = 840 
  = 12 (x + y) = 840 
            x + y  = 70 
 
x 0 70 
y 70 0 
 
Equation – (ii) 
  3x + 6y = 300 
  3 (x + 2y) = 300 
  X + 2y      = 100 
 
x 0 100 
y 50 0 
Equation (iii) 
  8x + 4y   = 480 
  4(2x + y) = 480 
  2x + y     = 120 
 
x 20 60 
y 80 0 
The shaded portion in the diagram represents the feasible region. 
 
The  shaded  portion  in  the  diagram  (on  previous  page)  represents  the  feasible  region,  and  the  matrix  of 
the extreme points 
Ei,i = 1, 2, 3, 4, 5 is  
Statement of possible profit at all points 
Point Number of units Contribution Per Unit Total Contribution 
(a × c) + (b × d) x (a) y (b) x (c) y (d) 
E1 0 0 5 7   0 
E2 0 50 5 7 350 
E3 40 30 5 7 410 
E4 50 20 5 7 390 
E5 60 0 5 7 300 
Since  410  is  the  largest  element  in  EC,  the  maximum  value  is  achieved  at  the  extreme  point  E3 whose 
coordinates are (40, 30).  
Thus to maximize profit, the company should produce 40 units of X and 30 units of Y.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
7. Answer any four out of the following five questions: 
a) Answer the following independent situation relating to an assignment problem with a 
minimization objective. 
i) Just after row and column minimum operations, we find that a particular row has 2 
zeroes. Does this imply that the 2 corresponding numbers in the original matrix before 
any operation were equal? Why? 
 
ii) Under the usual notation, where A32 means the element at the intersection of the 3rd row 
and 2nd column, we have, in a 4*4 assignment problem, A24 and A32 figuring in the 
optimal solution. What can you conclude about the remaining assignments? Why? 
 
Answer:  
i) Prerequisite  of  assignment  of any  job  is  each  row  and  column must  have  a  zero  value  in  its 
corresponding  cells. To  obtained  zero  in  every  row  and  column row  operation  and  column 
operation  are  carried  on.  It  is  not  essential  two  corresponding  numbers  in  original  matrix, 
before  any  operation  should  be  equal  to  make  two  zeros  in  the  same  row.  Two  may  derived 
because of only row operation or row and column operation also. 
ii) In  the  given  assignment  matrix  two  allocations  have  been  made  in  a24 (2nd row  and  4th 
column)  and  a32 (3rd row  and  2nd column).  This  implies  that  2nd and 3rd row  and  4th and 
2nd column are unavailable for further allocation. 
Therefore, the other allocations are at either at a11 and a43 or at a13 and a41. 
 
 
b) Classify the following under appropriate categories in Balanced Score Card: 
Ans:  
(i) Research and Development Innovation and Learning Prospective 
(ii) New product introduction  Internal Business Prospective 
(iii) Price Customer Prospective  
(iv) Cost Leadership Innovation and Learning Prospective 
(v) Sales penetration  Internal Business Prospective 
(vi) Profitability Financial Prospective 
(vii) Sales Financial Prospective 
(viii) Quality Customer Prospective 
 
c) How would you use the Monte Carlo simulation method in inventory control? 
 
Ans: In  order  to  provide  efficient  service  to  the  customers  it  is  necessary  to  choose  to  re-order 
point with proper consideration of demand during lead time. 
If  the  lead  time  and  demand  of  inventory  per  unit  time  both  are  random  variables  then,  the 
simulation  technique  can  be  applied  to  determine  the  effect  &  alternate  inventory  policy  on  a 
stochastic inventory system.
AMA-2016(M) Suggested Answer 
 
CA Ravi Shanker 
[Topper of EIRC & NIRC] 
The basic approach under this system is to find the probability distribution of the input and 
output functions of the past data. 
 
d) Indicate 2 activity drivers respect of each  of the  following activity  cost pools: 
Solution:  
i) Manufacturing cost   Number of hours worked 
 Number of units produced 
ii) Human resource cost  Number of employees 
 Number of employees working hours 
iii) Marketing resources cost  Number of advertisement 
 Number of sales personnel 
 Sales revenue 
iv) Accounting costs  Number of branches 
 Number of transaction  
 Seles revenue  
 
e) What is penetration pricing? What are the circumstances in which this policy can be adopted? 
 
Answer:  
Meaning of penetration pricing 
- Penetration pricing is a policy of low prices when the product is first launched in order 
to obtain sufficient penetration into the market. 
- It is opposite to skimming pricing. 
  
 Circumstances in which a penetration policy may be appropriate:   
(i) The demand is highly elastic and so would respond well to low price. 
(ii) If the firm wishes to discourage new entrants into the market. 
(iii)If  the  firm  wishes  to  shorten  the  initial  period  of  the  product‟s  life  cycle  in  order  to 
enter growth and maturity stages as quickly as possible. 
(iv) When there is substantial savings on large-scale production, here increase in demand is 
sustained by the adoption of low pricing policy.