PERT vs CPM vs BUDGET

yasaswi gomes (My grammar is 💯 good I)   (7290 Points)

06 July 2021  

Looks like CPM is close to Budgeting, doesnt it?

Activity Critical Path Method Budget - Deterministic method
Days Most likely (M) Actual work Completed Project cost (Days * Costs) Stage of completion %
A Purchasing material and warehousing at site


7 3,00,000 20%
B Bulldozing to prepare constructing foundation


3 50,000 3%
C Laying foundation





15 100000 7%
D Foundation watering time




15 20000 1%
E 1st tower layer





10 300000 20%
F 2nd tower layer





10 300000 20%
G Final tower layer and installing satellite equipment

12 400000 27%

Total Estimations





72
14,70,000 100%

Project evaluation and Review Technique (PERT) - Probability model Optimistic (O) Most likely (M) Pessimistic (P) PERT Estimates = (O+4M+P)/6 Sigma  (P-O/6) Pert variance
A Purchasing material and warehousing at site

5 7 11 24 1.0 1
B Bulldozing to prepare constructing foundation

2 3 7 4 0.8 0.7
C Laying foundation




10 15 25 17 2.5 6.3
D Foundation watering time



10 15 30 21 3.3 11.1
E 1st tower layer




7 10 20 12 2.2 4.7
F 2nd tower layer




7 10 20 12 2.2 4.7
G Final tower layer and installing satellite equipment
9 12 20 13 1.8 3.4

Total








101 14 32

STANDARD DEVIATION= 3.7 days








Probability of completing project in 102 days= 102-101/SD 0.268866






Using Z- Table, 0.27= 99.6% probability that work can be completed in 102 days 



















Probability of completing the work in 72 days= 72-101/SD -7.79713






Using Z- Table, -7.79713 = 0.832 








So, 1-0.832= 0.168 or 16.80% probability that work will be completed in 72 days