Help on Realavent costing

Final 614 views 5 replies

hi frnds...

m c.a. final student 4m surat!

m going through the chaptr relavent costing nw a days! bt m finding it very difficult.. can any1 explain me the objective n concept of tis approch.. y v do n wat v do????

i  knw d meaning of relavent cost n irrelevant cost bt nt able 2 solve it wen all comes mix in d form of big sum

Replies (5)

Relevant costing is used in management accounting when deciding between two options in the future.

All sunk costs are ignored as they are common to both options.

All non-cash items such as depreciation are ignored as they are not part of future cash flows

Opportunity costs are included - These are costs you incurr as a result of not persuing the alternative, these come in the form of lost profits or savings on costs you would have otherwise incurred

U shud read the question carefully then u will b able to distinguish betw sunk, and other such costs...

Ask ur doubts...will try to clear dat ...ok

 

ok m keeping part of questin here..

estimate

skilled labour 12 lakhs

Additional info:

skilled workers will b transfered to tis project from another project . Manager claimed that if the men wer returned to him he could have earned the company additional rs. 2 laks in the terms of profit.

For labour the following will be helpful,

General Rule is labour is Variable Cost and therefore it is relevant.

If it is excessive labour/idle, Then it is committed cost...therefore dat is irrelevant

If it is skilled labour and is yielding contribution inother depts u shd take variable cost +opportunity cost as relevant cost

thrfor....in this case it is 12+2=14 lakhs..

Originally posted by : chippy

For labour the following will be helpful,

General Rule is labour is Variable Cost and therefore it is relevant.

If it is excessive labour/idle, Then it is committed cost...therefore dat is irrelevant

If it is skilled labour and is yielding contribution inother depts u shd take variable cost +opportunity cost as relevant cost

thrfor....in this case it is 12+2=14 lakhs..

The relevant cost will be only 2 lakhs as labour expenses have already been incured( in her question the word used is transfered)

Opp. cost of 2 lakhs will alone be considered

but i think 12 lakhs is the estimate for the new project...so 12+2 shd b considered....


CCI Pro

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register