Can ne1 tell me how the question of PERT (Q.4) solved in the RTP May 13 CA Final AMA
Thnx in advance
CS BHAVIK HARSHAD SHAH
(Company Secretary)
(1662 Points)
Replied 09 April 2013
hii nikita
its nothing but its told about creashing the activities
so
dont go for this method but go for your method or clas method so you will understand properly.
so do it own your way
Sathish M
(Management Accountant)
(40581 Points)
Replied 09 April 2013
It is a resource smoothing Problem, where by a time scaled diagram needs to be drawn, for evaluating the resource allocation optimally.
NIKITA
(CA )
(302 Points)
Replied 12 April 2013
Thanks for your replies. Sathish I don't hv ne idea about resource smoothening. It would be nice if you could explain further.
Bhavik I don't know how should I proceed as I could not find the relevant data for solving through crashing. What is the data given in table about labourers???
CS BHAVIK HARSHAD SHAH
(Company Secretary)
(1662 Points)
Replied 12 April 2013
hii,
no its not labourers.
some is asking about to rearrange the activity by taking in to mind labour as well as carpenters, so we ave to focus on activities that how we can reduce labourer as well as carpenters.