recently govt provide multi vehicle provision in eway bill.
but not clarify in his example on eway bill portal that how to carry goods from warehouse/factory to book goods in train on multi vehicle.
example of ewaybill portal only describe that you can use multi vehicle option after arrival of goods at destination.
similarly there is no provision for export cargo movement on multi vehicle under single tax invoice from factory to customs house.
now what should be done by exporter because option of delivery challan is also blocked by waybill portal on supply of export
Steps:
1. First generate the e-way bill with source and destination as per the document/invoice.
2. Carry out the first leg of movement of the consignment up to the transshipment.
3. Choose the ‘Change to Multi-vehicle’ option and update the e-way bill for multi-vehicle
movement. Here, the total quantity of the consignment and movement from and to
place for the multiple vehicles requirement has to be entered
4. Now, when the consignment has been loaded to the smaller vehicle, update the ‘PartB’ of the e-way bill with the vehicle number, along with the quantity loaded, and move
the consignment.
5. Step No 4 may be repeated till total quantity is loaded and moved. The system will not
allow the quantity to be shipped in multiple vehicles more than what has been
declared while marking the e-way bill for mulit-vehicle.