Hi,
While computing EOQ, why do we muluiply Carrying cost with 1/2 in solving Q. I always forgot to divide it and my answer comes wrong ? What is the logic behind this ? Pl help...
Regards,
Patricia
Mumbai
Patricia (C.S.- Professional) (sdd) (197 Points)
18 September 2009Hi,
While computing EOQ, why do we muluiply Carrying cost with 1/2 in solving Q. I always forgot to divide it and my answer comes wrong ? What is the logic behind this ? Pl help...
Regards,
Patricia
Mumbai
sahil
(final)
(130 Points)
Replied 18 September 2009
while computing EOQ we divide d quantity as we r assuming that quantity will remain half in godown and half at factory. and carrying cost is for d godown quantity only.
MANIKANDAN
(STUDENT)
(55 Points)
Replied 20 September 2009
said by sathil is correct but the term is we have to take only average stock. That's why we are using 1/2.
anuj jain
(no)
(161 Points)
Replied 20 September 2009
manjkadan is correct and sathil is entirely wrong
sahil
(final)
(130 Points)
Replied 21 September 2009
anuj its a logic of taking average stock and if m worng then pls tell wats d logic of taking average stock . dude ur learning formules and m giving d perfect logic