Q37. A contractor has entered into a long term contract at an agreed price of175000 subject to an escalation clause for materials and wages as spelt out in the contract and corresponding actuals are as follows:

Materials               SQ(UNITS)         SP(RS.)           Actual Oty        AP(Rs.)

A                             5000                       5                         5050              4.80 

B                             3500                       8                          3450                7.90  

C                            2500                        6                         2600                 6.60 





LABOUR                  STd HOURS       HOURLY RATE     ACTUAL HOUR   HOURLY RATE

X                                      2000                                  7                         2100                      7.20

Y                                     2500                            7.50                          2450                      7.50

Z                                     3000                             6.50                       3000                        6.60





Reckoning the full actual consumption of materials and wages the company has claimed a final price of177360. Give your analysis of admissible ecalation claim and indicate the final price payable.