Hi all,

Please clarify whether Marketing expenses incurred for a particular project can be considered direct costs for calculation of percentage completion method as per AS 7.

Replies (1)

No. Marketing expenses (or selling expenses) cannot be considered as part of direct cost. Para 19 of AS-7 reads as under:

 
"Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:
(a) general administration costs for which reimbursement is not specified in the contract;
(b) selling costs;
(c) research and development costs for which reimbursement is not specified in the contract; and
(d) depreciation of idle plant and equipment that is not used on a particular contract"
 
 
Point (b) explicitly excludes selling costs from direct cost / contract related costs and hence should not be considered for percentage of completion

Leave a Reply

Your are not logged in . Please login to post replies

Click here to Login / Register  

Company
16 September 2026
Internal Audit - Team Lead

Consulting & Beyond

Chennai

CA

View Details
Company
Featured 03 October 2026
Accountant

A P Lodha and Associates

Jalna

B.Com

View Details
Company
30 September 2026
Senior Accounts Executive

Codeboard Technology

Chennai

MBA

View Details
Company
ARTICLESHIP 15 September 2026
Freelance Taxation Content Writer Intern

Interactive Media Pvt Ltd.

New Delhi

CA Inter

View Details
Company
22 September 2026
Account Assistant

Chirag P Shah & Co. Chartered Accountant

Pune

B.Com

View Details
Company
18 September 2026
Accounts & Finance Specialist

ULTRA CHEMICAL WORKS

Thane

CA Final

View Details
Company
ARTICLESHIP 21 September 2026
CA Article Assistant

KK & Company Chartered Accountant

Pune

CA Inter

View Details
Company
Featured 21 September 2026
Consultant - Reporting

Finrep Advisors LLP

Mumbai

CA

View Details