x ltd. undertook 2 contracts for construction of bridge & road, follwing are on 31-3-2010
contract 1 contract 2
contract price 560 900
cost incurred 410 50
estimated future cost 290 910
progessive payment 375 45
what amt. should be recognised as provision for loss
ans. contract 1 loss to be recognized rs.82 lakh & provision=58 lakh
contract 2 provision 60
why the 2nd contract the provision is 60 lakh