As 16

hardik majithiya (CA FINAL STUDENT) (340 Points)

25 April 2014  

Expenses incurred in 3 phases of construction of project of power plant are given below

 

Phase A

Phase B

Phase C

Total

Cash payment

50,00,000

70,00,000

85,00,000

 

Transfer of assets

45,00,000

12,00,000

10,00,000

 

 

 

 

 

 

Total

95,00,000

82,00,000

95,00,000

2,72,00,000

 

 

Money borrowed @ 14%    2, 50,00,000

 

The phase A is complete. How the borrowing   cost should be capitalized?

Answer given in rawat

Phase B     10,55,148

Phase C     12,22,426

MY ANSWER

Phase B     11,48,000

Phase C     13,30,000

 

Where is my mistake ?    

If possible give me detailed answer

thanx