Dear Mr. Mayur Buha,
We have an agreement with a Supplier A to buy a Material X for a period of 3 years at Rs Z rate.
As per the agreement, Supplier should supply the material at Rs Z rate till the expiry of the agreement period. But, after 2 years from the commencement of the agreement, the supplier demands a higher rate citing his raw material rate increase. As we told him we can not give rate increase as per the agreement, he replied that he is going to apply Force Majeure due to Power disruptions and stop supplies to us.
Under this circumstance, can we ask the supplier that you can not apply Force Majeure selectively for us ?
Awaiting your early response.